AN INCREASE TO THE AUTHORIZED PROJECT CONTINGENCY RELATED TO THE CONSTRUCTION CONTRACT FOR TENANT IMPROVEMENTS AT 200 NORTH CHERRY AVENUE / GAMUT CONSTRUCTION COMPANY, INC.
Meeting Date: February 3, 2009
Section: Consent Calendar
Approve an increase of $225,000 to the authorized project contingency related to Contract No. RDA 0607-09 with Gamut Construction Company, Inc., of Montclair, CA, for tenant improvements at 200 North Cherry Avenue; and revise the total contract authority to include a base contract award of $3,843,000 and a total revised contingency of $993,600 ($768,600 original plus $225,000) for a total of $4,836,600.
|
|